QUESTION
Do pipeline operators really have to get "off-pipe"
facilities into compliance to meet new regulations?
ANSWER
Pipe within the facilities is covered by the regulations, but
the equipment is not. The new ruling includes "compressor
units, metering stations, regulator stations, delivery stations,
holders and fabricated assemblies.
|
Off-pipe
to be included
It is clear that the new Pipeline Integrity regulations apply not only
to cross-country interstate pipelines, but also to "off-pipe"
facilities attached to the pipeline. These are "compressor units,
metering stations, regulator stations, delivery stations, holders and
fabricated assemblies." This means that operators will have to
document and track the same information for these off-pipe facilities
that is done for cross country pipelines. It also means that given the
single definition of a Potential Impact Circle (PIR), large diameter
equipment, such as a filterseparator or dehy tower, may greatly increase
a facility's PIR.
The assessment
of pipelines is limited to those that are within an High Consequence
Areas (HCA). Most compressor stations are located away from homes and
businesses. This will keep most of them out of the HCA's and therefore
out of the requirements for assessment and monitoring. The number of
meter stations that are included in HCA's is much larger. This is due
to the nature of the meter station being the transition from transmission
pipeline to distribution pipeline - from cross country rural pipeline
to urban pipeline. It is also expected that these last transmission
pipeline miles to the meter stations will be the most difficult to assess.
Other off-pipe facilities will probably fall into an HCA to the same
percentage as the pipelines themselves. Initial assessments for HCA's
need to be complete by June 17th, 2004, so this should be a top priority.
Regulatory
impact
The impact of the Rule is that those offpipe systems that are in HCA's
will have to go through an initial assessment and follow on assessments
in accordance with the Rule. Underground facilities will most likely
be assessed using Direct Assessment (DA). Even this is not as easy as
it sounds, as visual inspection of portions of the affected pipes is
the final step in DA. For aboveground facilities, visual inspection
is more reasonable. Hydrostatic testing off off-pipe systems is not
expected to be popular and in-line inspection is just not feasible.
The good news is that for the data integration and data evaluation requirements
of the Rule, most operators should be able to append the facility information
to their existing asset management systems. Managing the assets then
becomes a GIS (Geographic Information Systems) and IT (Information Technology)
exercise in maintaining and managing the appropriate databases (both
spatial and non-spatial). Even though the rule allows for manual evaluation,
this is expected to be a data management-intensive operation because
of the requirements of the Rule for data integration, analysis and continuous
improvement. To do this continuously - as required by the Rule - and
efficiently - as required by management - spatial and non-spatial applications
coupled with the right analytical software tools will be key.
Operators
should document the materials and construction specifications for each
facility, including all the pipe, fittings and equipment in compressor,
metering and regulator stations. Required data should include the pipe
and fitting size, strength or grade, and wall thickness. For manufactured
equipment like compressor cylinders, compressor cases and gas coolers,
the data will be similar but in a different format. Starting early will
give pipeline operators a head start on a potentially daunting task.
However,
information gathering on a pipeline facility will need to overcome one
basic problem- although regular pipelines, such as those that travel
across the country, are defined by distance markers and stations, piping
inside stations usually have no such assignments. Since compressor and
metering stations are usually built as an assembled piping structure
and not on a per-foot basis, some operators have no easy way of documenting
the specific components of their facility. To resolve this, operators
can begin to document facilities as if they were pipelines by assigning
line numbers. Though the process will require station walk downs, review
of as-built drawings, and culling of all available information from
databases, assigning line numbers can help operators manage the information
required by the Rule.
for more information about "Pipeline Integrity Inside The Fence"
download "The Basics" technical newsletter
Pipeline
Integrity Inside The Fence
(59k)
To
discuss how Basic Systems, Inc. can help you wade through these issues
and get your facilities into compliance, contact:
Tom Stemmer, Sr. Project Manager
tstemmer@bsicos.com
(740) 685-2511 ext. 302
or
Tim Arrowood,
Marketing Manager
tarrowood@bsicos.com
(740) 685-2511 ext. 336 |
Regulatory Excerpts
Part
192.201
"This subpart prescribes minimum requirements for an integrity
management program on any gas transmission pipeline covered under this
part."
Part
192.3
“Pipeline means all parts of those physical facilities through
which gas moves in transportation, including pipe, valves, and other
appurtenance attached to pipe, compressor units, metering stations,
regulator stations, delivery stations, holders, and fabricated assemblies."
"Transmission
Line means
a pipeline, other than a gathering line, that:
(a) Transports
gas from a gathering line or storage facility to a distribution center,
storage facility, or large volume customer that is not downstream from
a distribution center;
(b) Operates
at a hoop stress of 20 percent or more of SMYS; or
(c) Transports
gas within a storage field.
Related
Links
"Pipeline
Integrity
Frequently Asked Questions
http://primis.rspa.dot.gov/gasimp/
faqlist.gim
(Notice Question #6)
PART 192--TRANSPORTATION OF NATURAL AND OTHER GAS BY PIPELINE:
MINIMUM FEDERAL SAFETY STANDARDS
http://ops.dot.gov/cfr99/part192.htm
|